We released the national Power Grid Corp in 2015 before the date of the investment objectives. The reporter learned that in 2015, the investment in the power grid of the State Grid will reach 420 billion 200 million yuan, up to 24% from the same period, and the amount of investment will be new to a new high. In 2014, the investment amount of the State Grid reached 338 billion 500 million yuan, up to 14.1% in 2013.
The 2015 annual work meeting of the State Grid revealed that the national grid in 2015 approved the construction of a total of 14 lines of "six exchanges and eight straight" projects. In terms of overseas strategy, in addition to the UHV projects in Brazil and other places, the national grid will start the grid project connected with other countries in 2015. That is, the global energy Internet mentioned before by the State Grid will take the first step in 2015.
In this regard, the State Grid stakeholders told the "daily economic news" reporter, global energy Internet Engineering at this time and start the current "The Belt and Road" plan.
Speeding up the construction of UHV
National Grid said that the plan started in 2015 110 (66) kV AC line and above 64 thousand kilometers, 3.5 million KVA substation capacity, line 13 thousand kilometers, DC converter capacity of 140 million kilowatts; (66) operation of 110 kV AC line and above 46 thousand kilometers, transformer capacity of 240 million kva. The Kuche - Kashi transmission line and other key projects are built to ensure the further improvement of the 750 thousand volt main network frame in the northwest.
According to China Securities Network News, the national grid 2015 plans to approve the construction of the construction of the "six exchanges and eight straight" total of 14 lines. From the specific plan, a quarter of approval to start the Mengxi - Tianjin south, Yu cross - Weifang exchange and Jiuquan - Hunan DC "two cross has been approved to start the two quarter;" three straight "project, for Ximeng - Jiangsu, Shanxi - Jiangsu, Shanghai - Shandong temple. The second half of 2015 approved the plan started four pay four straight project, respectively, Changsha Mengxi - Wuhan, Jingmen - Nanchang - Zhangbei - Changsha exchange, Nanchang, Yubei, Nanyang Jindongnan - Zhumadian - Nanjing - Xuzhou - Lianyungang, Taizhou - Ji'nan - Zaozhuang - Linyi, Weifang - and Hulunbeier exchange; - Qingzhou, Mengxi - Wuhan, Chengdu, East - South East HVDC project.
The above meeting also revealed that the construction of the UHV project of the national grid will also further accelerate. The three way project has been put into operation in 2016, and the "one to four direct" project has been put into operation in 2017.
According to the planning of the annual work meeting of the State Grid, 50 new generation of intelligent substations will be built in the year of 2015 for the smart grid. 60 million 600 thousand intelligent electric meters are installed to realize the automatic collection of 316 million household electricity information. The State Grid will also build a flexible DC demonstration project in Xiamen, complete the upgrading and upgrading of the 36 sets of land adjustment system, and speed up the construction of the "three line one ring" expressway intercity interconnection and fast charging network.
The annual work meeting of the State Grid also revealed that the construction of distribution network will also usher in a new climax in 2015. The State Grid will complete the construction and transformation of the distribution network of 30 key cities and 30 key cities. The coverage rate of distribution network automation in key cities is more than 50%. It takes two years to complete the comprehensive management of "low voltage" in rural areas. 5 million 50 thousand households solve the "low voltage" and 21 county power network and network connection problem of weak years; 45 thousand households and 18.8 million electricity task, the full realization of power within the scope of "household electricity".
Realize the interconnection between power grid and foreign countries
At the same time, the global energy Internet, which was previously mentioned by the national grid, will take the first step. The content of the meeting "daily economic news" reporter learned that, in 2015, the national grid will be carried out in Kazakhstan - Nanyang ekibastuzets + 1 million 100 thousand volts high voltage DC project, Russia ERKO Zipf - Hebei Bazhou - 800 thousand volt HVDC project, Mongolia - Tianjin and Xinjiang Xibe Ao package Yili - Pakistan Islamabad - 660 thousand volt DC project preparatory work.
According to the reporter, Liu Zhenya, the chairman of the State Grid, once called for "building the global energy Internet" on from July 27th to 31st held in Washington, D.C., in 2014.
In addition, in the 2014APEC business summit, Shu Yinbiao, general manager of the State Grid is clear, the State Grid will rely on UHV technology of long distance and large capacity, low loss to create "the transmission corridor The Belt and Road economic belt, grid implementation and the 5 Central Asian countries, sharing Kazakhstan large energy base and the region's rich wind energy and solar energy resources, or to achieve a long-term and in Russia and Mongolia in the network.
State Grid stakeholders told the "daily economic news" reporter, the national energy Internet is different from the previous national grid of the overseas project, and this project started and is currently building a "The Belt and Road" economic trends are related.
It is understood that in 2014, the national grid successfully won the first UHVDC transmission project in Brazil, the beautiful mountain and water power transmission project, which is the first time that UHV technology has gone out of the country. At the same time, the national grid also successful part of the acquisition of Italy energy network company, Singapore international energy company assets in Australia and Singapore Australian energy company such as equity, and with Russian Power Grid Corp, Kazakhstan state's sovereign wealth fund, Egypt power and energy cooperation agreement signed by the Department of energy. By the end of 2014, the overseas assets of the State Grid had reached $29 billion 800 million.